KCGF Construction Updates

On April 1, 2018 installation of the Engineered Material Arresting System (EMAS) will begin at CGF. Please keep in mind, outside of the few weekend closures this is a construction project with a displaced threshold not a closure. If there is any information in the schedule that is unclear please call The Cleveland Jet Center 216-261-8800, we will be happy to answer any questions. If there are any changes to the schedule we will post them immediately on this web page. We hope that you will continue to use KCGF as it allows, The Cleveland Jet Center will be open for business as usual.

Updated Printable EMAS Construction Schedule

 

Updates to the above schedule:

The closure for June 23-25 is cancelled, the new closure dates will be as follows:
July 6 closing at 2200
July 7 closed
July 8 closed
July 9 opened at 0700

The runway lengths will remain at:
6- landing and takeoff 5297
24- landing 4615, take off 5297

July 9 we will open at 3700 ft for 6 and 24

 